  • Spring 2016: Final design completed
  • Fall 2016: Project bid & Contractor selected
  • Spring 2017: Construction site preparation and fabrication of bridge parts begins
  • Summer 2017: Bridge closed for 4 weeks - July 10 - August 6. Travel lanes temporarily reduced to one-way alternating traffic for 2-3 weeks before and after bridge closure. Construction completed by end of summer.